The method of implementation was made as a requirement to meet the technical administration of the auction in order that in the assessment of whether service providers can carry out the work to be carried out.Implementation of the method is an action plan that is used as a reference in the implementation of a construction project. Methods of execution include a breakdown of activities by activity, time allocation and working methods for the work - the main job. Basic considerations used in the execution of construction work was the realization of a building according to plan with consideration of the effectiveness of time and cost efficiency. This implementation method contains descriptions of the strategy of pre-work contractor from s / d post-work (maintenance period), to carry out the work to fit the image of planning, requirements and completed on time in accordance with the contract.
A. WORK PRE EXECUTION
Before implementation begins contractor will prepare, organize a strategy to carry out the work, both in terms of technical and financial terms. Steps taken by the contractor to include:Make a plan of work time: Time Scheduleï, Preparing personnelï, Preparing equipmentï, Preparing Cash Flowï, etc.Time schedule and curve "S" made rationally between the work with one another. In the time schedule is displayed weight divided by the work that needs time so that we can monitor each time the job exceeds or later than the time we had planned.
B. PREPARATION WORK
C. DAM BUILDING WORK (NEW)
Rocky Soil Excavation
Excavation Rocky is the excavation of soils containing rocks off by using the power of his being or heavy equipment are like Excavator PC 100 / PC 200 (depending on needs). The service provider must do this by following the excavation plan drawings.
Modalities
Pair job is stone masonry work time / mountain by using a mixture of cement sand that is formed in accordance with the image Implementation
Modalities:
Plastering job is a job plestran at the top of the wall, ujungujung masonry channel corresponding to the picture execution
Modalities:
is a land fill jobs are jobs that are dug hoard by using materials urugan of the furrows on the construction of the channel by human power (Manual) then compacted with tools.
Modalities
C. CHANNEL PARTNERS JOBS (KERMIR) P = 381 M 'Kr
Ordinary Soil Excavation
Ordinary Excavation is digging the soil with the use of heavy equipment for human or are like Excavator PC 100 / PC 200 (depending on needs). The service provider must do this by following the excavation plan drawings.
Modalities
Pair job is stone masonry work time / mountain by using a mixture of cement sand that is formed in accordance with the image Implementation
Modalities:
Plastering 1; 4
Plastering job is a job plestran at the top of the wall, ujungujung masonry channel corresponding to the picture execution
Modalities:
is a land fill jobs are jobs that are dug hoard by using materials urugan of the furrows on the construction of the channel by human power (Manual) then compacted with tools.
Modalities
A. WORK PRE EXECUTION
Before implementation begins contractor will prepare, organize a strategy to carry out the work, both in terms of technical and financial terms. Steps taken by the contractor to include:Make a plan of work time: Time Scheduleï, Preparing personnelï, Preparing equipmentï, Preparing Cash Flowï, etc.Time schedule and curve "S" made rationally between the work with one another. In the time schedule is displayed weight divided by the work that needs time so that we can monitor each time the job exceeds or later than the time we had planned.
B. PREPARATION WORK
- Measurement / UitzetOn the construction of irrigation networks in. ciburuluk (32 ha) measurement or uitzet at a job site measurements performed include pengkuran dimensions of length, width and height measurements irrigation is done by using a meter, theodolite, and whaterpass in order to get maximum results measurements were performed referring to the working drawings.
- Kisdam job or DryingOn the construction of irrigation networks in. Ciburuluk (32 ha) to do the job kisdam or land drainage by using a water pump or Alcon work aims to facilitate drying of masonry work and other work.
- Job Board Names ProjectAt work in the irrigation network. Ciburuluk (32 ha) to do the job board manufacturing project name, project name boards to inform the work activity to the general public.
- Documentation and Reporting. Documentation and Reporting At work in the irrigation network. Ciburuluk (32 ha) is done in the form capture and report daily, weekly and monthly during the work progresses
C. DAM BUILDING WORK (NEW)
Rocky Soil Excavation
Excavation Rocky is the excavation of soils containing rocks off by using the power of his being or heavy equipment are like Excavator PC 100 / PC 200 (depending on needs). The service provider must do this by following the excavation plan drawings.
Modalities
- Excavation rocky soil that can not be used as urugan material should be disposed of outside the working area
- Material from the excavation to be used as an ingredient urugan must be approved by the board of directors.
- Any material that is surplus to requirements should be dibuan urugan material by the service provider to a location specified by the board of directors.
- Service Provider should be responsible for all arrangements, acquisition of permits for the disposal of material from the owner of the land where the disposal is done.
- services provider in carrying out excavation work to be undertaken is quite safe from avalanches especially on a machine stand.
- When the work is completed, the service provider must notify the board of directors for examination.
Pair job is stone masonry work time / mountain by using a mixture of cement sand that is formed in accordance with the image Implementation
Modalities:
- Stones used should clean rock and hard and have been approved by the Board of Directors.
- Sand used to be good and have been approved by the Board of Directors.
- Species / mortar stone masonry work must be of a mixture of cement and sand with a volume ratio of 1 pc: 4 Mkt using a concrete mixer
- Couple stones should be arranged such that the stone with stone homogeen terisispesi basis, so the stones do not coincide / bersentuhan.Susunan raen stone (rock face) must have a distance (the width of the grout between 1-2 cm)
Plastering job is a job plestran at the top of the wall, ujungujung masonry channel corresponding to the picture execution
Modalities:
- Sand used to be good and have been approved by the Board of Directors.
- Species / mortar stucco work must be from a mixture of cement and sand with a volume ratio of 1 pc: 4 Mkt using a concrete mixer
- The stucco work done in two layers up to a thickness of 2 cm. If not told otherwise couples should be plastered on the top of the wall, the ends of the channel partner, and to 0.10 meters below the top of the wall or trepi as stated in pictures
- Plastering Job 1: 3 should be flat, straight, smooth and neat so that the top of the wall, the ends of channels covered masonry surfaces.
- Preparation of concrete had to adjust to the results of tests laboratoriumuntuk get quality / good quality, will be the type of material which shall be used;
- Concrete mixture ratio ditrntukan in the employment contract.
- Stirring is done using a concrete mixer (concrete molen), for mendapakan results / good quality;
- Concrete is used as a blanket on the reinforcement berfungsisebagai load-bearing structure and function as campurankedap water or leakproof;
- The concrete used in the building structure concreting / pengecoranharus using a concrete vibrator (vibro concrete) for mendapatkanhasil maximum.
- Reinforcement or pembesian installed and assembled for the building jenistulangan used in buildings. Distance and bentuktulangan / pembesian must follow the pictures that have been ditentukankebenarannya as well as approval of the board of directors.
is a land fill jobs are jobs that are dug hoard by using materials urugan of the furrows on the construction of the channel by human power (Manual) then compacted with tools.
Modalities
- Stockpiles material taken from the excavation that has been approved by the board of directors.
- Soil excavation results is spread and compacted using tools
- The size and the height adjusted to the working drawings and approved by the board of directors
C. CHANNEL PARTNERS JOBS (KERMIR) P = 381 M 'Kr
Ordinary Soil Excavation
Ordinary Excavation is digging the soil with the use of heavy equipment for human or are like Excavator PC 100 / PC 200 (depending on needs). The service provider must do this by following the excavation plan drawings.
Modalities
- Excavation regular land that can not be used as urugan material should be disposed of outside the working area
- Material from the excavation to be used as an ingredient urugan must be approved by the board of directors.
- Any material that is surplus to requirements should be dibuan urugan material by the service provider to a location specified by the board of directors.
- Service Provider should be responsible for all arrangements, acquisition of permits for the disposal of material from the owner of the land where the disposal is done.
- services provider in carrying out excavation work to be undertaken is quite safe from avalanches especially on a machine stand.
- When the work is completed, the service provider must notify the board of directors for examination.
Pair job is stone masonry work time / mountain by using a mixture of cement sand that is formed in accordance with the image Implementation
Modalities:
- Stones used should clean rock and hard and have been approved by the Board of Directors.
- Sand used to be good and have been approved by the Board of Directors.
- Species / mortar stone masonry work must be of a mixture of cement and sand with a volume ratio of 1 pc: 4 Mkt using a concrete mixer
- Couple stones should be arranged such that the stone with stone homogeen terisispesi basis, so the stones do not coincide / bersentuhan.Susunan raen stone (rock face) must have a distance (the width of the grout between 1-2 cm)
Plastering 1; 4
Plastering job is a job plestran at the top of the wall, ujungujung masonry channel corresponding to the picture execution
Modalities:
- Sand used to be good and have been approved by the Board of Directors.
- Species / mortar stucco work must be from a mixture of cement and sand with a volume ratio of 1 pc: 4 Mkt using a concrete mixer
- The stucco work done in two layers up to a thickness of 2 cm. If not told otherwise couples should be plastered on the top of the wall, the ends of the channel partner, and to 0.10 meters below the top of the wall or trepi as stated in pictures
- Plastering Job 1: 3 should be flat, straight, smooth and neat so that the top of the wall, the ends of channels covered masonry surfaces.
is a land fill jobs are jobs that are dug hoard by using materials urugan of the furrows on the construction of the channel by human power (Manual) then compacted with tools.
Modalities
- Stockpile Material taken from the excavation that has been approved by the board of directors.
- Soil excavation results is spread and compacted using tools
- The size and the height adjusted to the working drawings and approved by the board of directors